This corner in 2027 · Eleven arches and the soil on their roofs. The reclining figure in the middle is a KAWS sculpture. ©NOT A HOTEL · Mitsubishi Estate
This corner in 2027Eleven arches and the soil on their roofs. The reclining figure in the middle is a KAWS sculpture. ©NOT A HOTEL · Mitsubishi Estate
Daily Space

480 cubic metres of cedar in a building due to be taken apart (Tokyo · interim-use architecture)

2026.09.07

Two office blocks beside Tokyo Station closed in 2023 and came down. What is left is 10,784 m2 of land. The owner could have started the new tower straight away, but on 1 September it broke ground on something else: a single storey, 5 metres tall. It will stand for a few years and then be taken apart. That is the point. It was designed to come apart and go back up somewhere else.

1.On 1 September 2026 work began in Yurakucho 1-chome, Chiyoda-ku, Tokyo. The site sits directly outside the Central West exit of JR Yurakucho Station and covers 10,784 m2. The name is YURAKUCHO PARK. Completion is set for August 2027.
Where the land is · In a Marunouchi packed with towers, only the patch lit in yellow stays at ground level. ©Mitsubishi Estate
Where the land isIn a Marunouchi packed with towers, only the patch lit in yellow stays at ground level. ©Mitsubishi Estate
2.What stood here were the Yurakucho Building and the Shin-Yurakucho Building, completed in May 1966 and January 1967. Together they held 125,182 m2. Both closed on 31 October 2023, and demolition started in December 2024.
Before it closed · Emptied shops with the signage still up, inside the Yurakucho Building arcade. ©Dick Thomas Johnson · CC BY 2.0 · Wikimedia Commons
Before it closedEmptied shops with the signage still up, inside the Yurakucho Building arcade. ©Dick Thomas Johnson · CC BY 2.0 · Wikimedia Commons
Display case · A glass case left in place with everything cleared out of it. It went in when the building opened in 1966. ©Dick Thomas Johnson · CC BY 2.0 · Wikimedia Commons
Display caseA glass case left in place with everything cleared out of it. It went in when the building opened in 1966. ©Dick Thomas Johnson · CC BY 2.0 · Wikimedia Commons
3.What goes back up is one storey, about 5 metres high. Restaurants, shops and event space. Mitsubishi Jisho Sekkei is the architect, Taisei Corporation the contractor, and NOT A HOTEL handles planning and design.
Summer 2026 · The white surface inside the hoarding is the deck laid over the retained basement structure. ©Mitsubishi Estate
Summer 2026The white surface inside the hoarding is the deck laid over the retained basement structure. ©Mitsubishi Estate
4.Nobody backfilled the hole. The basement structure of the two demolished blocks stays where it is, capped over to serve as ground, and a concrete box running five levels down becomes the foundation for what comes next. An entire cycle of filling soil back in and digging it out again simply drops out of the programme.
Section · One timber storey above, five retained basement levels below. ©Mitsubishi Estate
SectionOne timber storey above, five retained basement levels below. ©Mitsubishi Estate
5.One bay was left standing. It is the span attached to the D2 exit of the Tokyo Metro Yurakucho Line, kept up to the second floor so the route to the ticket gates stays open. They cut down from the top only as far as they needed to.
The red dashes · Everything came out except this one bay, the one joined to the subway exit. ©Mitsubishi Estate
The red dashesEverything came out except this one bay, the one joined to the subway exit. ©Mitsubishi Estate
6.Eleven buildings sit on that deck. Each is an arched portal frame with soil on the roof, planted with grass and trees, built from 480 m3 of Japanese cedar CLT. CLT is normally a panel product for walls. Here it works as columns and beams.
Inside an arch · Timber overhead, all of it. What fills the glass is the sculpture's head and hand. ©NOT A HOTEL · Mitsubishi Estate
Inside an archTimber overhead, all of it. What fills the glass is the sculpture's head and hand. ©NOT A HOTEL · Mitsubishi Estate
7.Exposing timber over 100 m2 inside a fire prevention district requires separate certification of fire resistance. The developer says no CLT structure has been left exposed at this scale anywhere in Otemachi, Marunouchi or Yurakucho before. A building meant to last a few years went through the full permanent-building process.
8.Every joint comes undone. Bolts and connectors were newly designed so an arch can be dismantled whole and rebuilt elsewhere. Benches and planting come from twelve municipalities, from cedar out of Odate in Akita to Ryukyu pine from Ishigaki in Okinawa.
One unit, exploded · Arch, glass, floor plate, soil, edge frame. Assembled in that order and taken apart in it. ©Mitsubishi Estate
One unit, explodedArch, glass, floor plate, soil, edge frame. Assembled in that order and taken apart in it. ©Mitsubishi Estate
9.The 2026 published land price for commercial land in Yurakucho is 13.52 million yen per square metre. Multiply that across 10,784 m2 and you get 145.8 billion yen. Roughly KRW 1.25 trillion, converting 100 yen at 864 won.
10.From 31 October 2023, when the two blocks closed, to the park's opening in 2027 is four years. Through all of it, rent from 125,182 m2 came to zero. Land in the middle of the strongest office market in Tokyo sits idle for four years.
임대료가 0인 구간과 그 뒤 폐관에서 개업까지 4년, 그다음이 잠정이용이다 공백 4년 잠정이용 수년 신축 2023.10 폐관 2024.12 해체 2026.9 착공 2027 개업 헐린 연면적 12만 5,182㎡ 새로 짓는 것 지상 1층 · 높이 5m
How to read thisThe four years on the left ran with no income. The middle band is the stretch the new building has to earn in.
11.Marunouchi offices fetch 33,000 to 50,000 yen per tsubo per month. Vacancy in 2026 is 0.9%. So where does the cost of hoarding off more than 10,000 m2 for four years actually show up in this market? Not in the tax bill. In the rent nobody collected.
12.Restaurants, shops and event space now earn for the years until the tower goes ahead, and the corner keeps people walking through it. A short-life building normally disappears leaving only a demolition invoice behind, but the 480 m3 moves to the next site. It was built under the Forestry Agency's FY2024 demonstration programme for CLT buildings, which covered part of the construction cost.
13.Mitsubishi Estate has said it will put 600 to 700 billion yen into Yurakucho and Tokiwabashi by 2030. More than KRW 5 trillion. The company says the tower planned for this site will exceed 100,000 m2 of floor area.
14.What pulls people in, in the end, is a name. A KAWS sculpture will lie in the middle of the yard, and JAPA VALLEY TOKYO, created by Pharrell Williams and NIGO, opens inside in 2027. Whether a few-year facility can carry names of that weight is what decides an interim project.
Night · The sign lit on the glass at left is JAPA VALLEY TOKYO. ©NOT A HOTEL · Mitsubishi Estate
NightThe sign lit on the glass at left is JAPA VALLEY TOKYO. ©NOT A HOTEL · Mitsubishi Estate
15.This is not the first run at it. The same company opened empty floors in its Yurakucho buildings from 2020 under the name Yurakucho Micro STARs Dev., and in February 2022 launched Yurakucho Art Urbanism, putting artist studios inside the Yurakucho Building while it waited to close. They learned there how to use the years in which a building is dying. Now they have moved the method onto land where the building is already gone.
Ticket gates · The central gates of JR Yurakucho Station. Step out of them and the site is across the road. ©Mister0124 · CC BY-SA 4.0 · Wikimedia Commons
Ticket gatesThe central gates of JR Yurakucho Station. Step out of them and the site is across the road. ©Mister0124 · CC BY-SA 4.0 · Wikimedia Commons
국내에서 같은 땅을 놀릴 때 종합부동산세 토지분은 빈 땅이냐 건물 밑이냐로 갈린다 빈 땅 · 종합합산 기본공제 5억 원 · 최고 세율 3% 건축물 부속토지 · 별도합산 기본공제 80억 원 · 최고 세율 0.7% 막대는 기본공제 크기 비율이다. 세율은 공제 뒤 과세표준 구간에 따라 달라진다
How to read thisLeaving the land empty gives you one sixteenth of the deduction and a top rate more than four times higher.
16.Two office blocks vanished from 10,784 m2 beside Tokyo Station, and a single storey built to be taken apart in a few years goes up in their place. It fills a four-year gap at less than a thousandth of the 125,182 m2 that came down. Try the same sequence in Korea and the sticking point is how long you are allowed to keep it. A structure like this is normally filed as a temporary building, good for three years, then extended three years at a time as many times as the local ordinance permits. The Japanese side certified fire resistance and built it as a permanent structure, which is why KAWS and Pharrell Williams could be attached to it. Names of that size do not go into a facility that refiles an extension every three years. The tax follows the same line. Empty land is assessed on the aggregate basis with a 500 million won deduction; put a building on it and qualify the land as attached to that building, and the separate basis gives you 8 billion won.
Daily Space #041 · 2026.09.07
Sources. Mitsubishi Estate press releases (28 Jul 2025 · 28 Aug 2026), Mitsubishi Jisho Sekkei project material and supplied images, Impress Watch (28 Jul 2025 · 28 Aug 2026), Nikkei xTECH (Jul 2025), Toyo Keizai Online, Bijutsu Techo and Tokyo Art Beat (Jul 2025), Yurakucho Art Urbanism executive committee material, MLIT published land prices 2026, Japan CLT Association notice on the FY2024 CLT building demonstration programme, National Tax Service rate tables for the comprehensive real estate holding tax, Enforcement Decree of the Building Act on temporary structures, Seoul Money Brokerage base rate (4 Sep 2026).
The currency conversion (100 yen at 864 won) and the land value total are figures multiplied out from public data and may differ from actual transaction or book values.